August 31, 2011 - The building exterior and early landscaping have been completed, while work progresses on the new lobby, interior offices, and spacious, new showroom area.
August 15, 2011 - The iconic red Bystronic rectangle now stands proudly above the new main entrance, while ceilings and ductwork are being completed on the Elgin facility’s interior.
July 21, 2011 - The Elgin facility’s roof and floors have now been completed, and the concrete poured for the grand entrance stairway.
July 13, 2011 - In just two weeks, installation of the outer walls have been completed, along with the supporting structure for the facility's roof.
June 29, 2011 - Following the ceremonial groundbreaking this past January, site preparation progressed despite inclement winter and spring weather, allowing installation of the prefabricated outer wall modules to begin in June. |
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||